lightning107ef
lightning107ef lightning107ef
  • 03-10-2018
  • Mathematics
contestada

A company can produce as many as 50 mountain bikes and as many as...

A company can produce as many as 50 mountain bikes and as many as class=

Respuesta :

musiclover10045
musiclover10045 musiclover10045
  • 03-10-2018

The other constrain would be the number of hours it takes to make each one.

4 hours for a mountain bike would be 4x

5 hours for a road bike would be 5y

The hours need to be less than or equal to a total of 300 hours.


The missing constraint would be 4x + 5y ≤ 300.

Answer Link
Asdfjkadfjkakjf Asdfjkadfjkakjf
  • 29-10-2018

Answer:

4x + 5y ≤ 300

Step-by-step explanation:

x: no of mt bike n y: no. of road bike

4 labor hrs for 1 mt bike n 5 labor hrs for 1 road bike

company has at most 300 labor hrs per day

so the contraint is 4x + 5y ≤ 300


Answer Link

Otras preguntas

School or summer (I’m fr this is a question on my homework)
what is 75% of 36 briefly explained?
b. Bettie's Boutique is having a 20% off sale. original price sale price $15 $12 $25 $20 $35 $28 what is the constant of proportionality?
Find the solution for this mathematical assignment
28-day-cycle schedules are subdivided into four groups___________
Which detail from the movie supports the opinion that Eleanor Roosevelt played a crucial role in her husband’s political career?
How do you recognize a relative clause of characteristic?
Couples or partners with shared money or finances being dishonest with each other. A) Financial infidelity B) Trust deficit C) Money secrecy D) Economic dishone
What kingdom was the glory age of ancient Egypt?
What is the measure of A. 70° B. 150° C. 160° D. 175°