8 men complete a work in 40 days. How many days will be taken to complete the samed work if 2 more men join them.

Respuesta :

rpband00
rpband00 rpband00
  • 04-04-2018
Hello there,

There were 8 men who completed a task in 40 days. If you divide 40/8 that is 5 so it took them 5 weeks to complete this task.

Now if you add two more men, that makes it 10 men to complete the work in 50 days. If you divide 50/10 that is 5.
10 days

Hope this helped!

Answer Link

Otras preguntas

What caused Portugal to finallywithdraw from its African colonies?
What caused Portugal to finallywithdraw from its African colonies?
What is 5.207 as a fraction?
What is sociocultural ?
if cosx=1/12 and sinx>0 find tan2x
The volume of a rectangular prism is 270 cubic centimeters. The height of the prism is 5 centimeters. What should the length and width of the prism be? Explain
You are given an aqueous solution of NaCl. The simplest method for the separation of NaCl from the solution is (A) evaporation of the solution to dryness (B) c
how do you write a fraction as a mixed number
How close to North Korea is Inchon?
Donald Johanson, Tom Gray, and others discovered a hominid that lived in East Africa__________ million years ago and nicknamed her Lucy, whose scientific name t